Completed Projects

Construction of Three New 132kV/11kV Substations and Related 132kV Overhead Power Lines in SEK 132kV Cable Termination Works, Um Al Hayman Substation

Three New 132kV/11kV Substations, Um Al Hayman Substation, Kuwait
Client Larsen and Toubro
Location Kuwait
Date 2022

Scope of Work

Installation Portion:

Installation of 12 units of 132kV GIS cable sealing ends, Connex 6-S type.

Installation of 12 units of 132kV ESP-type outdoor oil-immersed cable sealing ends.

Cable specification: 1×800mm² Cu XLPE power cable.

Cable accessories supplied by PFISTERER.